- Customer
- Persimmon Homes, Taylor Wimpey, Hallam Land Development
-
- Procurement Route
- Negotiated
-
- Completion Date
- August 2012
-
- Quantity Surveyor
- Hydrock
-
- Value
- £5.3 million
-
- Form Of Contract
- JCT 2005 with contractor’s design
-
- Project Manager
- Mike Owen
-
- Area
- School 2,230 sq m multi-purpose building 780 sq m
-
- Program Duration
- 42 weeks
-
- Architect
- Stride Treglown