Project

Southwark Council

  • Customer
    London Borough of Southwark
  • Procurement Route
    Two stage
  • Completion Date
    01/08/2009
  • Quantity Surveyor
    Towner Townsend
  • Value
    £10m
  • Form Of Contract
    GC/Works/1 2 stage Design & build
  • Project Manager
    Towner Townsend
  • Structural Engineer
    Towner Townsend
  • Area
    173,000 sq ft
  • Program Duration
    45 weeks
  • Architect
    BDG Workfutures
  • ME Engineer
    John Packer Associates