- Customer
- The Silver Spoon Company
-
- Procurement Route
- Single Stage Design & Build
-
- Completion Date
- August 2009
-
- Quantity Surveyor
- Lorien Engineering
-
- Value
- £2 million
-
- Form Of Contract
- J5 CT 200Design & Build
-
- Project Manager
- Lorien Engineering
-
- Structural Engineer
- MLM
-
- Area
- 12,150 sq ft
-
- Program Duration
- 38 weeks
-
- Architect
- Feilden & Mawson
-
- ME Engineer
- Johns Slater and Haward