- Customer
- Confidential
-
- Procurement Route
- 2 Stage
-
- Completion Date
- July 2014
-
- Quantity Surveyor
- Davis Langdon LLP
-
- Value
- Confidential
-
- Form Of Contract
- NEC
-
- Project Manager
- Davis Langdon LLP
-
- Area
- Confidential
-
- Program Duration
- 52 weeks
-
- Architect
- TTSP
-
- ME Engineer
- Arup
Overview
A higher education institution engaged us to construct a new data center to centralise its data storage requirements into one location.
The project
The two-storey data center was constructed on a green field site and housed four data halls on the ground and first floors. Supported on piled foundations, the building accommodated approximately 240 racks, associated ancillary space and a plant, providing 3.2 MW of power.
External works included providing the necessary infrastructure connections as well as security fencing around the perimeter of the site.