data centre 2
Project

Higher education institution, UK

  • Customer
    Confidential
  • Procurement Route
    2 Stage
  • Completion Date
    July 2014
  • Quantity Surveyor
    Davis Langdon LLP
  • Value
    Confidential
  • Form Of Contract
    NEC
  • Project Manager
    Davis Langdon LLP
  • Area
    Confidential
  • Program Duration
    52 weeks
  • Architect
    TTSP
  • ME Engineer
    Arup

Overview

A higher education institution engaged us to construct a new data center to centralise its data storage requirements into one location.

Data center 2

The project

The two-storey data center was constructed on a green field site and housed four data halls on the ground and first floors. Supported on piled foundations, the building accommodated approximately 240 racks, associated ancillary space and a plant, providing 3.2 MW of power.

External works included providing the necessary infrastructure connections as well as security fencing around the perimeter of the site.