- Customer
- GlaxoSmithKline (GSK)
-
- Procurement Route
- Traditional tender and single interview
-
- Completion Date
- Phase 1 - August 2016; phase 2 - November 2016
-
- Quantity Surveyor
- Douglas Wilson of GSK
-
- Value
- £2m
-
- Form Of Contract
- NEC3 with amendments
-
- Project Manager
- Ian Little of Arcadias Ltd
-
- Structural Engineer
- Mike Wakely of Ross & Co
-
- Area
- 277 sq m
-
- Program Duration
- Original phase 1- 20 weeks and phase 2 - 19 weeks
-
- Architect
- Richard Mason of Simons Group
-
- ME Engineer
- Mechanical Consultant Ben Finney; Electrical Consultant Steve Lakin both of CPW Ltd