100 Queen Street - office fit out and extension - ISG - Glasgow
Project

100 Queen Street

The 100 Queen Street scheme covers an impressive 64,000 sq ft.
  • Customer
    Esson Properties Limited
  • Procurement Route
    Traditional 1
  • Completion Date
    25th November 2016
  • Quantity Surveyor
    McCue & Porter
  • Value
    £8.5 million
  • Form Of Contract
    SBCC Standard Building Contract with Quantities 2011 edition with Amendments
  • Structural Engineer
    Acies
  • Area
    64,000 sq ft
  • Program Duration
    53 weeks
  • Architect
    CDA
  • ME Engineer
    Cundall
100 Queen Street - office fit out and extension - ISG - Glasgow - Results

Introduction

100 Queen Street was crowned Best Refurbished and Recycled Workplace at the Scottish BCO Awards shortly after ISG completed the Cat A fit out and two-storey extension.

The regal development is now worthy of its city centre location with stunning Grade A office accommodation including two new penthouse floors.

Spanning six floors with open plan office spaces and four retail units at ground and basement levels, the finished scheme covers an impressive 64,000 sq ft. 

100 Queen Street - office fit out and extension - ISG - Glasgow - Challenges

The project

Originally built in the 1920s, the building required substantial structural alternations to accommodate the additional weight of the two-storey extension.

As well as work to allow the building to expand, our team was also tasked with M&E installations and works to reconfigure the existing space to accommodate the new retails units.

Working on a tight site on one of the busiest streets in Glasgow, above live retail units, also posed challenges for our teams.

100 Queen Street - office fit out and extension - ISG - Glasgow -  What we did

Added value

The team also undertook alterations to the top floor plate in preparation for construction. This included the removal and replacement of existing curtain walling facade, wall and roof cladding, and the relocation of the plant room.

To deliver the rooftop extension, we erected cantilever scaffolding and a concrete base in the basement. This base, with 15m deep piling, was designed to hold the crane for the 26 weeks that it was on site.

As the scheme was delivered within a live environment, the existing basement access route through the building to neighbouring properties was maintained during the works.

100 Queen Street - office fit out and extension - ISG - Glasgow - Sustainability

Sustainability

Internal site set up was constructed using reclaimed and recycled materials such as floor tiles, ceiling tiles and doors.

“We are absolutely delighted that the whole team involved in this project has been recognised by the BCO in producing what some regard as one of Glasgow’s most compelling Grade A office buildings in a commanding location overlooking Royal Exchange Square, directly opposite the Gallery of Modern Art. This award is significant for a building that keeps on delivering.”

Hunter Esson, chief executive of Esson Properties