The project
Delivered in two phases, the programme of works comprised the demolition and redevelopment of the existing store along with the new highway construction and was delivered in two phases.
Phase one, completed in 32 weeks, entailed building the structure and the car park – accommodating 780 cars and filling stations – on stilts. The 20-week long second phase included the demolition of the store and ground remediation in preparation for further retail development. Additionally, both phases included the highway construction.
The project had a fast-track delivery programme, ongoing for 52 weeks.